Full length and Sectional Main Line Structural Pipe Rehabilitation
Installation of the cured-in -place liner is performed
by either inversion with water, air or winched in place
and cured with steam or hot water. During the cure process
the tube is held tightly against the host pipe by either
water or steam pressure. Lateral connections leave dimples
that are reopened by the use of robotic cutters.
Applications:
Sewer, Water, Storm and other product pipelines 4"
through 48" in diameter and up to over 1,000 feet
in length can be rehabilitated using this method. Sectional
liners are also available in lengths 3' to 50' in length
anywhere within a longer run. Liners can be made to accommodate
a variety of design considerations including the ability
to negotiate bends and transitions in pipe diameter.
Standards: Full length Greenbook section 500-1.4 ASTM
standards F 1216, F 1743, D 5813 Sectional liners: ASTM
2599-06